Kitchen Remodeling in Los Altos, CA
Los Altos kitchens tend to be remodeled for the long run. Many homes here are older single-story houses on generous lots, and the kitchen is often the room that has fallen furthest behind the rest of the house.
Design by M&M remodels kitchens across Los Altos with dedicated crews and a front-loaded process: design and selections are settled, the permit is in hand and cabinetry has a delivery date before anything is torn out.
CSLB License #1082131 · Licensed, bonded and insured · 22+ years of experience · 1,000+ projects completed
Who This Is For
- Opening a closed-off kitchen to the living or dining space
- Reworking a layout that has never quite functioned
- Remodeling a kitchen as part of a wider renovation or home addition
- Replacing cabinets, counters and appliances as one coordinated, designed project
- Bringing together a kitchen that has been part-updated over the years and no longer hangs together
- Modernizing the kitchen in an older Los Altos home, including the electrical and plumbing behind the walls
Standalone kitchen or part of a bigger project — both are normal work for us.
What a Kitchen Remodel Includes
A kitchen remodel touches almost every trade in the house, which is why the planning matters as much as the build. A full project in Los Altos normally includes the following.
Scope of work
- Layout planning and design
- Cabinetry — custom, semi-custom, or supplied
- Countertops and backsplashes
- Appliance planning, fitting, and coordination
- Plumbing relocation and fixture installation
- Electrical, including dedicated circuits and lighting design
- Ventilation and range hood venting
- Flooring
- Structural work where walls are being removed
- Permit applications and inspection coordination
Standalone or part of a larger renovation — both are normal work for us. Many Los Altos kitchens are remodeled alongside a room addition or a garage conversion, so the whole project is designed and scheduled together.
Permits and Requirements in Los Altos
Non-structural kitchens can be permitted quickly. The City of Los Altos says non-structural kitchen renovations can generally be reviewed and permitted within 72 hours. Plans and the application go to the Building Division in PDF form.
Moving walls changes the path. Removing or relocating load-bearing or non-load-bearing walls can move a kitchen into standard plan review, and removing a bearing wall needs additional plans. Establishing which walls are structural is one of the first things we check.
Exterior changes need Planning approval. A new window, door or other exterior change goes to the Planning Division before the building permit.
The city spells out kitchen electrical requirements. Los Altos requires at least two 20-amp circuits for countertop receptacles, GFCI protection for countertop outlets and those near the sink, AFCI protection for kitchen outlets and devices, and a dedicated circuit for a plug-in range hood. The handout notes the existing panel may need an upgrade or a sub-panel.
Smoke and carbon monoxide alarms are part of the permit. A kitchen remodel permit brings the home’s smoke and CO alarms up to current requirements, interconnected and with battery backup.
Title 24 energy requirements apply to lighting and certain equipment in a kitchen remodel. We design to them rather than retrofitting after an inspection.
We confirm current requirements with the Los Altos Building Division for every project.
How We Run a Kitchen Project
- Consultation — how you use the kitchen, what is not working, and a realistic budget range
- Design — layout, cabinetry, appliances, and finishes
- Selections locked before demolition — this is the step that protects the schedule
- Permit — often within about 72 hours for a non-structural kitchen, longer when walls move
- Ordering — cabinetry and appliance lead times drive the start date, not the other way around
- Demolition and rough-in — plumbing, electrical, structural
- Inspections — coordinated by us
- Installation and finishes — cabinetry, counters, appliances, tile, trim
- Walkthrough — punch list and closeout
We do not start demolition until cabinetry is ordered and a delivery date is confirmed. Tearing out a kitchen and then waiting ten weeks for cabinets is the single most common way these projects go wrong, and it is entirely avoidable.
What Affects the Cost
- Cabinetry — the largest single line on most kitchen budgets, and the widest range
- Whether the layout stays or plumbing and gas move
- Whether a wall is coming out, and whether it is load-bearing
- Countertop material and quantity
- Appliance selections
- Electrical capacity and whether the panel needs upgrading
- Ventilation, especially where new ducting is required
- Flooring
- Condition of what is behind the existing cabinets
Cabinetry and layout changes are where the budget is decided. Everything else moves the number far less than people expect.
Design in 3 simple steps
Consult & Design
We start with a thorough consultation, creating custom designs tailored to your style and needs.
Expert Construction
Our skilled team manages every detail, from demolition to installation, ensuring precision and quality.
Enjoyment
We complete your project with meticulous attention, ensuring your complete satisfaction and a stunning new kitchen.
Area We Serve: San Francisco | San Mateo | Redwood City | Palo Alto | Menlo Park | Atherton | Mountain View | Sunnyvale | Los Altos | Cupertino | Saratoga | Los Gatos | San Jose
Frequently Asked Questions
If you don’t see your question answered here, please don’t hesitate to contact us directly – we’re always happy to help!
Yes. Design by M&M holds California contractor license #1082131 and is licensed, bonded and insured. You can check the status of any California contractor's license yourself at cslb.ca.gov — we would encourage it, for us or anyone else you are considering.
More than 22 years of building in the Bay Area, across more than 1,000 completed projects. That covers additions, ADUs, custom homes, and full renovations, which is why we can usually tell you early whether what you have in mind is realistic for your property.
That is the question worth planning around, and it depends more on ordering than on construction. We sequence so that demolition happens once materials are secured, which keeps the kitchen-less period as short as the project allows. We give you a realistic figure after design, not an optimistic one at the first meeting.
Yes. Los Altos says non-structural kitchen renovations can generally be reviewed and permitted within 72 hours. Removing or relocating walls can move the project into standard plan review.
Often, yes — but whether it is load-bearing determines the cost and the permit path. That is one of the first things we establish, because the answer changes the project substantially.
Sometimes not. Older Los Altos homes frequently need panel or circuit work to support modern appliances. We check capacity during the consultation so it is in the budget from the start.
Yes. We will flag anything that will not work with the layout or the requirements before it is ordered, which is cheaper than finding out on delivery day.
Yes, both.
Almost always. We set up containment and talk through temporary kitchen arrangements during planning — a sink, a fridge and a microwave somewhere workable makes a large difference.